A1081 Luton Road, Harpenden

Drainage works are due to start on Monday 14 August - Friday 22 September 2017.

The first 3 weeks of works between the Rail Bridge and the junction with Cooters End Lane, works will be completed under 3-way lights, mostly during 9.30am and 4pm (network restricted hours).

In some locations, 3-way lights will be left for 24 hours because of the nature of the works.

Between 4 - 22 September, works will be managed under 2-way lights and localised traffic management.

What's happening?


The purpose of the works is to improve the drainage infrastructure along Luton Road and help with the highway flooding reported at this location.

Why is it happening?


Phase 1 works were completed along Luton Road, Harpenden in August 2016, between Hollybush Lane and Clarence Road junctions. These works are a continuation of Phase 1 works in advance of resurfacing works.